Description:
|
The project will relocate and replace existing Pump Station 14 located in East Bremerton, WA. The new pump station will include two vertical turbine pumps with variable frequency drives (VFDs), an interior standby generator, provisions for secondary chlorination and a public ADA accessible bathroom. An approximately 800 square foot pump station building will be constructed of concrete masonry unit (CMU) walls with a concrete slabon-grade floor. Additional onsite improvements will consist of new asphalt pavement, two stormwater bioretention areas and approximately 600 linear feet of new 8-inch ductile iron water main.
|
Publication Date/Time:
|
9/16/2022 9:00 AM
|
Closing Date/Time:
|
10/13/2022 2:00 PM
|
Contact Person:
|
Michele Filley, Telephone: (360) 473-2349, E-mail: michele.filley@ci.bremerton.wa.us
|
Related Documents:
|
|
|